NCCS Timeline: Designation Notices Due by 13 June 2028 — the Deadlines That Follow and What NIS2 Requires Until Then
In short
- On the network code on cybersecurity timeline, competent authorities must notify high-impact and critical-impact electricity entities no later than 13 June 2028 (Article 24(6) of Regulation (EU) 2024/1366).
- Most entity deadlines run from that notice: risk report and crisis plan in 12 months, cybersecurity management system in 24.
- Until then, NIS2 Articles 20, 21 and 23 reach in-scope electricity entities through national transposition laws, which Member States had to apply from 18 October 2024.
- Checked against: Regulation (EU) 2024/1366, ENTSO-E’s NCCS deliverables page and Directive (EU) 2022/2555.
Almost two and a half years after the Network Code on Cybersecurity (NCCS) entered into force, the formal notice that switches its obligations on for an electricity company is still to come. Under Article 24, that notice relies on thresholds from a Union-wide risk assessment report, and the report relies on risk assessment methodologies that the competent authorities only settled on 15 October 2026, according to ENTSO-E’s NCCS page. Counted on the maximum periods the Regulation allows, the chain runs past the fixed backstop in Article 24(6), so 13 June 2028 is the date to plan around.
This guide turns the relative deadlines of Commission Delegated Regulation (EU) 2024/1366 into calendar dates and shows which NIS2 duties apply in the meantime. Our NIS2 energy sector guide covers the wider scope and control questions for all five energy subsectors.
Does the network code apply to your company?
Plain-language summary: NIS2 applies to you because of your entity type and size. The NCCS applies only if your competent authority identifies you as high-impact or critical-impact.
Get the NIS2 Article 21 Compliance Checklist
90+ assessment items mapped to CIR 2024/2690 — instant PDF, no payment.
Article 2(1) of the NCCS lists the entity types it covers “if they are identified as high-impact or critical-impact entities in accordance with Article 24”. Article 2(1) of NIS2 works differently: it applies to the entity types in its annexes that are medium-sized or larger. Recital 7 of the NCCS states that its criteria refer only to an entity’s role in cross-border electricity flows, “without any consideration” of the NIS2 essential-entity criteria. The two lists overlap but are not the same:
| Entity type | NIS2 Annex I, point 1(a) | NCCS Article 2(1), once identified |
|---|---|---|
| Transmission and distribution system operators, producers | Listed by name | Not named separately; the CNMC lists transmission, distribution and producers among the candidate types |
| Electricity undertakings | Only those carrying out the function of “supply” | All electricity undertakings as defined in Article 2(57) of Directive (EU) 2019/944 |
| Nominated electricity market operators (NEMOs) | Listed | Listed, point (b) |
| Aggregation, demand response and storage providers | Listed as market participants | Not named separately; the CNMC lists aggregators among the candidate types |
| Recharging point operators | Listed | Listed, point (h) |
| Balancing responsible parties, organised market places | Not listed | Listed, points (g) and (c) |
| Managed security service providers | Annex I point 9 (ICT service management), not point 1(a) | Listed, point (j) |
| Critical ICT service providers, regional coordination centres, ENTSO-E, EU DSO entity | Not listed in Annex I | Listed, points (d), (i), (e) and (f) |
The practical takeaway: a balancing responsible party or a security provider to a grid operator can fall under the NCCS through a separate route from its NIS2 status, and because the NCCS has no size rule, an entity that NIS2 leaves out by size can in principle still be identified under it.
Identification uses the Electricity Cybersecurity Impact Index (ECII), measured in megawatts. The final ECII and thresholds will come from the Union-wide report (Article 19(3)(b)). Until then, the provisional ECII from ENTSO-E and the EU DSO Entity gives a working estimate. For a DSO, the index is the maximum DSO load over the previous year. For a producer, it is the sum of the maximum capacity of all its generating units. The document calls these values a recommendation that is “not legally binding”. A sample of its Table 2:
| Member State | Provisional high-impact threshold | Provisional critical-impact threshold |
|---|---|---|
| Germany, France, Italy, Netherlands | 1,500 MW | 3,000 MW |
| Spain, Poland | 1,000 MW | 3,000 MW |
| Austria | 500 MW | 3,000 MW |
| Ireland | 500 MW | 700 MW |
| Malta | 250 MW | 250 MW |
A producer in Spain with 1,200 MW of maximum generating capacity would sit above the provisional high-impact line and below the critical-impact line. The same fleet in Germany would sit below both. Treat that as a planning signal, not a classification: the final thresholds may differ.
Where the NCCS timeline stands in November 2026
Plain-language summary: the start-up deadlines have mostly passed, the methodologies were settled in October 2026, and the Union-wide risk assessment that drives designation comes next.
The Regulation was published in the Official Journal on 24 May 2024 and entered into force on the twentieth day after publication (Article 49), which is 13 June 2024. These are the dated milestones so far:
| Date | Milestone | Legal basis | Status |
|---|---|---|---|
| 13 June 2024 | Entry into force | Art. 49 | Done |
| 13 Oct 2024 | Provisional ECII recommended to competent authorities | Art. 48(2) | Published by ENTSO-E |
| 13 Dec 2024 | Member States designate a competent authority; provisional list of high- and critical-impact processes | Art. 4(1), 48(4) | Designation still pending in Spain (see below) |
| 13 Feb 2025 / 13 Mar 2025 | Provisional national lists of candidate entities; candidates notified | Art. 48(3) | Voluntary track |
| 13 Mar 2025 | Risk assessment methodologies proposed | Art. 18(1) | Public consultation workshops held 13 Nov and 2 Dec 2024 |
| 13 June 2025 | ACER benchmarking guide; cyber-attack classification scale methodology; provisional list of standards | Art. 13(1), 37(8), 48(6) | ACER guide published 13 June 2025 |
| 13 June 2026 | Feasibility study on a common information-sharing tool | Art. 37(9) | Published, dated 13 June 2026 |
| 15 Oct 2026 | Competent authorities’ final position on the Article 18 and 37(8) methodologies | Art. 8 | Done, per ENTSO-E |
| 31 Dec 2026 | Exercise scenario template for entity-level exercises | Art. 43(5) | Due |
Two items in this table matter for planning. First, the candidate lists under Article 48(3) are a voluntary track: identified candidates “may voluntarily fulfil their obligations” on a precautionary basis, and Article 48(10) asks all covered entity types to “strive to progressively apply” the non-binding guidance. Second, national approval of the methodologies is happening now. The CNMC announced on 30 October 2026 that it had approved both methodologies. It did so as Spain’s default competent authority, “ya que aún no se ha producido la designación” (no authority has yet been designated under the code). Article 4(1) provides for exactly that fallback to the national regulator. Our Spain energy compliance guide covers the Spanish NIS2 track that runs alongside.
Why 13 June 2028 is now the date to plan around
Plain-language summary: if every step after the methodologies takes the full time the Regulation allows, the nine-month notice window would end after 13 June 2028, so the fixed backstop decides.
Article 24(6) gives each competent authority nine months from receipt of the final Union-wide report to notify identified entities, “and in any case no later than 13 June 2028”. The report itself runs on three clocks in Article 19: a draft within 9 months of the methodologies’ approval, an ACER opinion within 3 months, and the final report within 3 months of that opinion. Counted on those maximums from the October 2026 approvals, our projection looks like this:
| Step | Rule | Projected latest date (our calculation) |
|---|---|---|
| Methodologies approved | Art. 8 | October 2026 (position 15 Oct; Spain 30 Oct) |
| Draft Union-wide risk assessment report to ACER | Art. 19(1): within 9 months | July 2027 |
| ACER opinion | Art. 19(4): within 3 months | October 2027 |
| Final report notified to competent authorities | Art. 19(5): within 3 months | January 2028 |
| Notice to high- and critical-impact entities | Art. 24(6): within 9 months, no later than 13 June 2028 | 13 June 2028 (backstop applies before the 9 months run out) |
13 June 2028 is the latest date by which each competent authority must notify the entities on its list that they have been identified as high-impact or critical-impact.
Source: Commission Delegated Regulation (EU) 2024/1366, Article 24(6)
Two caveats keep this honest. Any step can finish early, and an authority can notify as soon as it has the final report, so a notice in late 2027 or early 2028 remains possible. And the Regulation offers no stated escape from the backstop: Article 8(1) lets competent authorities jointly prolong the deadlines in Articles 18, 23, 29, 33, 34, 35 and 37 in exceptional circumstances, and Article 24 is not on that list.
This is also why older calendars disagree. The OpenKRITIS deliverables table of March 2026 projected the notification for mid-September 2027, with a draft Union-wide report in mid-June 2026. That schedule rested on methodologies listed as published by February 2026. The competent authorities’ final position came on 15 October 2026, so a September 2027 designation date should no longer appear in your plan as a deadline.
The entity calendar if you are notified on 13 June 2028
Plain-language summary: after notification, the entity-level deadlines spread over about four years; an earlier notice moves most of them forward by the same amount.
Most rows count from the latest lawful notice date. The exercise date follows the calendar year after notification, and the Article 31(1) date follows the adoption of the controls. Read the table as the outer limit of your project plan.
| Deadline (if notified 13 June 2028) | Obligation | Who | Legal basis |
|---|---|---|---|
| From notification | Share information on a reportable cyber-attack within 4 hours of becoming aware it is reportable | High and critical | Art. 38(3) |
| 13 Sep 2028 | Designate an EU representative (entities without an EU establishment) | Non-EU entities | Art. 15(1) |
| 13 June 2029 | Entity-level risk assessment report to the competent authority; entity-level cyber crisis management plan | High and critical | Art. 27, 41(6) |
| 31 Dec 2029 | First cybersecurity exercise with cross-border scenarios | Critical | Art. 43(1) |
| 13 June 2030 | Cybersecurity management system (CSMS) established | High and critical | Art. 32(1) |
| Up to mid-2032 | Be able to demonstrate compliance with the CSMS and controls on request: 24 months after the controls are adopted and the CSMS is established | Critical | Art. 31(1) |
The controls track runs on its own clock. The TSOs must propose minimum and advanced controls within 7 months of submitting the first draft Union-wide report (Article 29(1)), which on our projection means early 2028. The competent authorities then have six months to decide, or longer if ACER is asked for an opinion (Article 8(3) to (6)). Entities must apply the controls within 12 months of approval (Article 29(6)), so roughly between mid-2029 and early 2030 on our projection. The supply chain controls apply to procurement processes that start six months after the controls are adopted (Article 33(5)). A five-year grid equipment contract tendered in 2029 may therefore need NCCS clauses even though the CSMS deadline is a year away.
Authorities have later deadlines of their own: the Member State risk report within 21 months of notification (Article 20) and regional mitigation plans no later than 13 June 2031 (Article 22(1)). Before any of that, Article 24(1) lets a competent authority request information from an entity to determine its ECII values, so expect questionnaires before the notice itself.
What NIS2 requires meanwhile, and what carries over
Plain-language summary: NIS2 reaches most electricity companies through national transposition laws, and almost every NCCS duty has a NIS2 counterpart you can build now and extend later.
Member States had to apply their NIS2 measures from 18 October 2024 (Article 41). For a TSO, DSO, producer or supplier above the size cap, that means management-body approval and oversight of security measures (Article 20(1)), the measures in Article 21(2), and the 24-hour, 72-hour and one-month reporting chain in Article 23(4). The Annex I, point 1(a) list sets which electricity entity types are in scope. National transposition laws set the exact dates and registration steps in each country.
| NCCS duty (later) | NIS2 provision (now) | What to build now so it carries over |
|---|---|---|
| Entity risk management for the high- and critical-impact perimeter (Art. 26) and report (Art. 27) | Art. 21(2)(a): policies on risk analysis | An asset inventory tagged by business process, plus an impact estimate in MW using the provisional ECII |
| CSMS with senior management involvement (Art. 32) | Art. 20(1) approval and oversight; Art. 21(2)(a) | An ISMS whose scope statement names the grid processes and their interfaces with other entities |
| 4-hour sharing of reportable cyber-attacks (Art. 38(3)) | Art. 23(4)(a): 24-hour early warning | An incident form with a field for cross-border electricity impact |
| Supply chain controls for new procurement (Art. 33) | Art. 21(2)(d): supply chain security | Contract clauses that allow security requirements to be updated mid-term |
| Entity crisis management plan (Art. 41(6)) | Art. 21(2)(c): business continuity and crisis management | A crisis plan with a cyber scenario and named roles |
The reporting row deserves attention. Under Article 38(8), a NIS2 Article 23 notification that already contains the information required by Article 38(3) counts as the NCCS report. One well-designed form can serve both regimes. Recital 15 adds that NIS2 authorities “could” treat NCCS compliance as meeting the corresponding NIS2 requirements, or vice versa. That is a recital, so it signals intent and does not bind any authority. Our energy incident response guide covers the reporting chain step by step, and the energy sector checklist maps each Article 21 measure to grid-specific evidence.
Who does what before 2028:
- Compliance officer: check whether you were notified as a provisional candidate under Article 48(3), and put 13 June 2028, plus 12 and 24 months, in the compliance calendar. Effort: Low.
- CISO: extend the NIS2 asset inventory with process tags and a MW impact estimate, and test whether the incident process could file within 4 hours. Effort: Medium.
- Board: approve the NIS2 measures now under Article 20(1), and budget for a CSMS project starting no later than mid-2028. Effort: Low for the decision, High for the project.
Frequently asked questions
When will electricity companies be designated under the NCCS?
Competent authorities must notify identified high-impact and critical-impact entities within nine months of receiving the final Union-wide risk assessment report, and no later than 13 June 2028 (Article 24(6)). With the methodologies settled in October 2026, the backstop is the latest date to plan around; an earlier notice is possible.
Do NCCS obligations apply before an entity is notified?
Not as binding duties. Article 2(1) applies the Regulation to entities once they are identified under Article 24. Candidates on the provisional lists may apply it voluntarily under Article 48(3), and Article 48(10) asks all covered entity types to “strive to progressively apply” the non-binding guidance.
Does the NCCS replace NIS2 for electricity companies?
No. Recital 3 says the Regulation complements NIS2 regarding the electricity sector whenever cross-border electricity flows are concerned. NIS2 Articles 20, 21 and 23 apply now to in-scope electricity entities through national law, and a single NIS2 incident notification can also satisfy the NCCS reporting rule if it contains the required information (Article 38(8)).
Are the provisional ECII thresholds final?
No. ENTSO-E and the EU DSO Entity call them a recommendation that is not legally binding. The final ECII and thresholds will come from the Union-wide risk assessment report under Article 19(3)(b).
Next step
Put 13 June 2028 in the plan as the latest possible notice date, then work back from the 12-month risk report and the 24-month CSMS. Most of that work is the NIS2 programme you need anyway, built with process tags, MW estimates and a reporting form that serves both regimes. If you have not yet confirmed your NIS2 scope, start with the energy sector compliance guide.
This article provides general information only and does not constitute legal or regulatory advice. Requirements may vary by jurisdiction and organisation type. Consult a qualified legal professional or compliance specialist for advice specific to your situation.
Sources
- Commission Delegated Regulation (EU) 2024/1366 of 11 March 2024 establishing a network code on sector-specific rules for cybersecurity aspects of cross-border electricity flows, OJ L, 2024/1366, 24.5.2024 (EUR-Lex text, archived copy).
- ENTSO-E, Network Code on Cybersecurity: deliverables and final methodologies approved by competent authorities.
- ENTSO-E and EU DSO Entity, Provisional Electricity Cybersecurity Impact Index (ECII), Article 48(2) NCCS.
- CNMC, La CNMC aprueba las metodologías de evaluación de riesgos y clasificación de ciberataques en el sector eléctrico, 30 October 2026.
- ACER, ACER issues a guide on benchmarking cybersecurity investments in the EU electricity sector, 13 June 2025.
- ENTSO-E and EU DSO Entity, Feasibility study on a common tool, Article 37(9) NCCS, 13 June 2026.
- OpenKRITIS, EU Network Code on Cybersecurity (NCCS): timeline of deliverables, March 2026.
- Directive (EU) 2022/2555 (NIS2), Article 2: Scope.
- Directive (EU) 2022/2555 (NIS2), Article 20: Governance.
- Directive (EU) 2022/2555 (NIS2), Article 21: Cybersecurity risk-management measures.
- Directive (EU) 2022/2555 (NIS2), Article 23: Reporting obligations.
- Directive (EU) 2022/2555 (NIS2), Article 41: Transposition.
- Directive (EU) 2022/2555 (NIS2), Annex I: Sectors of high criticality.