Machinery Regulation Cybersecurity: 9 Clauses for Machine Purchase Orders Before 20 January 2027

In short

  • Machinery Regulation cybersecurity rules (Annex III, sections 1.1.9 and 1.2.1) apply to machines placed on the market or put into service from 20 January 2027.
  • They oblige the machine builder to protect safety functions against corruption, identify safety software and keep a five-year tracing log. They do not oblige it to patch.
  • For machines placed on the market before 11 December 2027, the Cyber Resilience Act’s vulnerability handling duties do not apply, so for a NIS2 operator the contract is the only enforceable right to security updates.
  • Checked against: Regulation (EU) 2023/1230, Directive (EU) 2022/2555, Commission CRA guidance C/2026/6013.

Purchase orders signed this winter for delivery after 20 January 2027 will bring in the first machines that EU law requires to collect evidence of interventions in their safety software. From 20 January 2027, Regulation (EU) 2023/1230 makes protection against corruption an essential health and safety requirement, so a new machine placed on the market from that date has to meet it to carry the CE marking. That covers the machine builder’s side. If your factory is an essential or important entity under NIS2, you have duties of your own: supply chain security and vulnerability handling under Article 21(2)(d) and (e), as transposed in your Member State. The two laws overlap only in part. The Machinery Regulation asks for a machine that resists tampering when it leaves the factory. It does not ask the builder to fix the vulnerabilities found afterwards. The purchase order is where you close that gap.

Which Machines and Which Buyers the Clauses Are For

The short version: what matters is the date the machine is placed on the market or put into service, not the date of your order. Whether you need the NIS2 hooks depends on whether your company is in NIS2 scope.

Machine placed on the market Machinery law Cyber Resilience Act (if the machine is a product with digital elements) What the contract has to add
Before 20 January 2027 Directive 2006/42/EC. No section 1.1.9 duty. Article 14 reporting applies from 11 September 2026. No vulnerability handling duty. Clauses 2 to 9, as plain contract terms (clause 1 applies only from 20 January 2027)
20 January 2027 to 10 December 2027 Regulation (EU) 2023/1230, including Annex III sections 1.1.9 and 1.2.1 Article 14 reporting applies. No vulnerability handling duty. All nine clauses. Clause 8 matters most, because it is your only right to security updates.
From 11 December 2027 Regulation (EU) 2023/1230 Full CRA, including a support period of at least five years, or the expected use time if shorter (Article 13(8)) All nine clauses. Clause 8 can refer to the CRA support period.

The middle row is the trap. The Commission’s CRA guidance, published in the Official Journal on 17 November 2026, states in paragraph 210 that where a product was placed on the market before 11 December 2027, “the manufacturer is not required to comply with the vulnerability handling obligations set out in Part II of Annex I”. The reporting duty of CRA Article 14 still applies to those products. So if the machine is a product with digital elements, the builder must report an actively exploited vulnerability, but nothing in the CRA requires it to ship a fix for a machine placed on the market in mid-2027.

Free Download

Get the NIS2 Article 21 Compliance Checklist

90+ assessment items mapped to CIR 2024/2690 — instant PDF, no payment.

✓ Check your inbox — the PDF is on its way.

11 December 2027 is the date the CRA’s vulnerability handling duties begin. Products with digital elements placed on the market before that date are not subject to them unless they undergo a substantial modification after it (CRA Article 69(2)).

Source: European Commission, CRA guidance C/2026/6013, paragraph 210

Is 20 January 2027 still the date? Machine builders’ associations asked the Commission to move sections 1.1.9 and 1.2.1(f) to the CRA’s 11 December 2027 date, and the ETUC opposed the request, as ibf-solutions reports. According to the draft minutes of the Expert Group on Machinery of 27 April 2026, the Commission said that “at present, no delay is foreseen to be endorsed”. The consolidated text of 27 July 2026 still gives 20 January 2027 in Article 54. Plan for that date unless an amending act appears in the Official Journal.

Who the NIS2 columns apply to: medium-sized and larger manufacturers of machinery (NACE C28), electrical equipment (C27), electronics (C26) and vehicles (C29) fall under Annex II, point 5, of Directive (EU) 2022/2555. So do chemicals and food producers under points 3 and 4. If your company is not in scope, the clauses are still good engineering practice, but no NIS2 supervisor will ask to see them. Note also that a machine builder in division C28 can be an NIS2 entity itself. The scope test for your own plant is in our NIS2 manufacturing compliance roadmap.

What Sections 1.1.9 and 1.2.1 Make the Machine Builder Do, and What They Leave to You

The short version: the builder must make the machine resist tampering that could make it unsafe, and must prove afterwards what was changed. Confidentiality, uptime and patching stay with you.

Section 1.1.9 of Annex III has five subparagraphs, and each one matters to a buyer. Connecting another device, directly or through a remote device, must not lead to a hazardous situation. Hardware that gives access to safety-critical software must be protected against accidental or intentional corruption, and the machine must collect evidence of any intervention in it. Software and data critical for compliance must be identified and protected. The machine must identify the safety software installed on it “at all times in an easily accessible form”. And it must collect evidence of any intervention in, or modification of, that software or its configuration. Section 1.2.1(a) adds that control systems must withstand “reasonably foreseeable malicious attempts from third parties leading to a hazardous situation”, “where appropriate to the circumstances and the risks”. Section 1.2.1(f) requires a tracing log of interventions and safety-software uploads, enabled for five years after each upload.

Three limits follow from the text. First, recital 25 of the Regulation as published in the Official Journal states that the measures are “limited to the protection of the safety of the product”. The draft guide chapter on section 1.1.9 (version of 18 October 2026, approved by the Editorial Group but still awaiting the Expert Group’s endorsement, according to the Editorial Group’s report of 22 October 2026) says the section “does not cover the confidentiality of data or intellectual property”, and gives no guidance on business continuity. Second, neither section contains an obligation to supply security updates once the machine is in service. The draft guide expects the measures to be effective over the whole product life cycle. On our reading, that is a design target for the machine as delivered, not a patching service. Third, the draft guide expects remote access to be delivered switched off (“security by default”), with “the user manual” describing “which measures must be taken by the user to ensure secure access”. Some of the security work is passed to you in the instructions.

The Nine Clauses to Put in the Purchase Order

The short version: seven of the nine clauses ask the builder to hand over, or keep up, something the Machinery Regulation already makes it build. That keeps the cost low and makes the request hard to refuse. Clauses 6 and 8 go beyond the Regulation, so expect to negotiate them.

Clause to write into the order Machinery Regulation basis NIS2 measure it supports (CIR 2024/2690 benchmark) Evidence at acceptance
1. Conformity basis. A machine placed on the market or put into service from 20 January 2027 comes with an EU declaration of conformity under Regulation (EU) 2023/1230. Partly completed machinery comes with an EU declaration of incorporation and assembly instructions. Art. 54, Art. 52(1), Arts 11, 21, 22 Art. 21(3): overall quality of suppliers’ products (6.1.2(e) assurance) The declaration cites 2023/1230, not 2006/42/EC
2. Interface list and secure delivery state. The builder lists every physical, logical, wired and wireless interface, including service and debug ports. Remote access is delivered deactivated, and the instructions state what you must do to keep access secure. Annex III 1.1.9, first subparagraph; draft guide “security by default” Art. 21(2)(e) (6.1.2(d): security functions and secure configuration) Interface list checked at the factory acceptance test. Remote access found switched off at site acceptance.
3. OEM remote service. Remote service runs only through your gateway, with named accounts, sessions recorded on your side, and no permanent tunnels. 1.1.9, first subparagraph (“any remote device”); 1.2.1(a) Art. 21(2)(d): relationship with service providers (5.1.4(a), (b)) Signed remote access procedure; first session in your access log
4. Safety software list and version readout. The builder names the software and data critical for compliance. The machine shows installed safety software versions on its display or as an exportable file, without special engineering tools. 1.1.9, third and fourth subparagraphs Art. 21(2)(i): asset management (6.1.2(c): hardware and software components) Version export loaded into your asset inventory
5. Intervention evidence. The builder states what the machine records about interventions in hardware, software and configuration, where the record is stored, and whether operation depends on an external logger. 1.1.9, second and fifth subparagraphs Art. 21(2)(b) incident handling and (c) business continuity A parameter changed during the site acceptance test shows up in the record
6. Tracing log access. The builder names where the five-year tracing log is kept, and gives you read access or a copy for your own incident analysis. 1.2.1(f) Art. 21(2)(b); facts for Art. 23(4) reports Storage location and retention stated in the handover file
7. Signed updates and a planned-change list. Updates are signed and verifiable. The builder lists the updates and configuration changes it foresees or plans, and states who checks the safety functions after each one. Art. 3(16), Art. 18; draft guide: “signature verification upon software updating” Art. 21(2)(e): maintenance (6.1.2(b)) Signature check shown at commissioning; list annexed to the contract
8. Vulnerability handling and notification. The builder supplies security updates until a stated end date, and tells you about vulnerabilities and incidents that affect the machine. None. The gap clause. Art. 21(2)(e) vulnerability handling; Art. 21(3) (5.1.4(d), (f); 6.1.2(b)) Support end date and a security contact written into the contract
9. Conformity route and security assumptions. The builder states how it met 1.1.9 and 1.2.1 (harmonised standard, IEC 62443-based route, an EU cybersecurity certificate or a notified body) and what its risk assessment assumes about your network. Art. 20(9); 1.2.1(a) Art. 21(1) state of the art and standards; Art. 21(3) secure development (6.1.2(e), (f)) Summary of the security risk assessment; certificate, if one is claimed

The CIR point numbers come from the Implementing Regulation (EU) 2024/2690. Under Article 1 it binds only digital-infrastructure and digital-service providers, not manufacturers. For a factory, those points are a checklist of what a careful supervisor might expect, not a legal duty. The full supplier-contract framework is in our NIS2 supply chain security guide, and the legal drafting side is in the vendor contract clauses guide.

Where clauses 5, 6 and 9 need care

Clause 5 has an availability catch. The draft guide says that where evidence is collected by external devices, the machine “can only be operational when the external data processing or monitoring has stored all necessary evidence”. If the builder’s design relies on a logging server on your network, that server now sits in the machine’s safety chain. It belongs in your business continuity plan, because an outage of that server could stop the line.

Clause 6 asks for more than the law gives you. Section 1.2.1(f) enables the log “exclusively to demonstrate the conformity of the machinery or related product with this Annex”, and only following a reasoned request from a competent national authority. On our reading, that purpose gives the operator no right to read the log, so a contract term is the only route. The draft guide adds that “it is irrelevant who made the change”, so your own engineers’ uploads end up in the log too.

5 years is how long the tracing log of interventions and safety-software uploads must stay enabled after each upload. Its stated purpose is to answer a competent national authority’s reasoned request.

Source: Regulation (EU) 2023/1230, Annex III, section 1.2.1(f)

Clause 9 exposes the assumptions that land on you. The draft guide allows the protection for one component to be “provided by another component (security appliance, e.g. a firewall) of the machinery”. A builder’s risk assessment may also assume that the machine sits in a segmented network zone, which only you can provide. Ask for those assumptions in writing and map them to your zone and conduit model. Our IEC 62443 to Article 21 mapping shows how. On standards: ibf-solutions reports that FprEN 50742 (the final draft of the future EN 50742) is at CENELEC’s approval stage and offers a route built on IEC 62443-4-1, 3-3 and 4-2. Until a harmonised standard is cited, the Expert Group minutes note that the new cyber-safety requirements “may necessitate Notified Body assessment, when harmonised standards are not fully applied”. Under Article 20(9), a certificate or statement of conformity under a cybersecurity certification scheme adopted under Regulation (EU) 2019/881, whose references are published in the Official Journal, creates a presumption of conformity with 1.1.9 and 1.2.1 only “insofar as those requirements are covered by” it, so ask which requirements the certificate covers.

The Update Trap: When Your Own Change Makes You the Manufacturer

The short version: a change the builder did not plan, made by physical or digital means, that creates a new hazard and needs new protective measures can turn your plant into the manufacturer of that machine. Clause 7’s list of planned changes helps you show that routine updates were planned.

Article 3(16) defines a substantial modification as a change “by physical or digital means” that is “not foreseen or planned by the manufacturer”, creates a new hazard or increases an existing risk, and requires either new guards or protective devices that need changes to the safety control system, or new measures for stability or mechanical strength. Under Article 18, whoever carries it out “shall be considered to be a manufacturer” and must run the conformity assessment. The only exception is a non-professional user modifying a machine for their own use, and a factory is not one.

On a plain reading, most software updates will not meet every part of that definition, because it also requires new protective measures. But whether a change was “foreseen or planned by the manufacturer” is something only the builder can document. Commission guidance on substantial modification was still a “revised draft for discussion” in the Editorial Group’s 22 October 2026 report. Until it is final, a written list of planned changes in the contract is the most useful evidence you can have. Our OT patch management guide covers the change workflow around it.

Who Owns Which Clause

Role Owns First action
Procurement / plant owner Clauses 1, 8 (end date, price of support) Add the nine clauses to the standard machine purchase terms
OT security lead / CISO Clauses 2 to 5, 9 Add interface, version-export and logging checks to the acceptance test scripts
Compliance / legal Clauses 6, 7 Draft the log-access and planned-change wording; check that national NIS2 law adds no supplier rules
Management body Risk acceptance where a builder refuses clause 8 Approve compensating controls or a different supplier (under NIS2 Article 20(1), the management body approves the risk-management measures)

Checklist Before 20 January 2027

  1. Now: list every machine on order with its expected delivery date, and sort them by the three rows of the scope table.
  2. Before the next order: put clauses 1 to 9 in your purchase terms. For orders already placed, send clauses 2 to 9 as a change request.
  3. Before delivery: extend the factory and site acceptance tests with the evidence column of the clause table.
  4. At delivery: record the builder’s support end date in your supplier register. Machines placed on the market before 11 December 2027 depend on clause 8 for security updates for as long as they run.
  5. Quarterly: check the Official Journal for an amendment to Article 54 and for the citation of EN 50742.

Frequently Asked Questions

Does the Machinery Regulation apply to machines we already own?

No, as long as you do not substantially modify them. Under Article 52(1), Member States may not impede the making available of products placed on the market in conformity with Directive 2006/42/EC before 20 January 2027. A substantial modification after that date brings Article 18 into play.

Is a machine that meets section 1.1.9 compliant with NIS2?

No. NIS2 Article 21 binds your company, not the product. A machine that meets section 1.1.9 gives you parts of the evidence for Article 21(2)(d) and (e). It does not cover patching, supplier monitoring or incident handling, which remain your measures.

Does a CRA-compliant machine meet sections 1.1.9 and 1.2.1?

Not automatically. CRA recital 53 says compliance “could facilitate” meeting them, and “such synergies have to be demonstrated by the manufacturer”. Ask the builder for that demonstration under clause 9.

What if the builder refuses clause 8?

Record the refusal, apply compensating controls such as segmentation and monitoring, and get the residual risk accepted by the management body. NIS2 Article 21(3) asks you to take into account “the overall quality of products and cybersecurity practices” of your suppliers, and a refusal is part of that assessment. Our CRA vulnerability handling guide explains what builders will owe once the CRA’s duties apply to their products.

This article provides general information only and does not constitute legal or regulatory advice. Requirements may vary by jurisdiction and organisation type. Consult a qualified legal professional or compliance specialist for advice specific to your situation.

Sources

  1. European Parliament and Council. Regulation (EU) 2023/1230 on machinery, consolidated text of 27 July 2026 (incl. corrigendum OJ L 169, 4.7.2023): Arts 3(16), 11, 18, 20(9), 21, 22, 52, 54; Annex III sections 1.1.9 and 1.2.1.
  2. European Parliament and Council. Regulation (EU) 2023/1230 on machinery, original text, OJ L 165, 29.6.2023, p. 1: recital 25.
  3. European Parliament and Council. Directive (EU) 2022/2555 (NIS2): Articles 20, 21, 23; Annex II.
  4. European Commission. Implementing Regulation (EU) 2024/2690: Article 1; Annex points 5.1.4 and 6.1.2.
  5. European Parliament and Council. Regulation (EU) 2024/2847 (Cyber Resilience Act): Articles 13(8), 14, 69, 71; recital 53.
  6. European Commission. Commission guidance on the application of Regulation (EU) 2024/2847 (C/2026/6013), OJ C, 17.11.2026, paragraph 210.
  7. Expert Group on Machinery. Draft minutes of the meeting of 27 April 2026, v1.00 (hosted by ibf-solutions).
  8. Machinery Regulation Editorial Group. Guide to application of the Machinery Regulation, Annex III 1.1.9 and 1.2.1(a) and (f), version of 18 October 2026, draft (hosted by ibf-solutions).
  9. Machinery Regulation Editorial Group. Report to the Machinery Experts Group, 22 October 2026 (hosted by ibf-solutions).
  10. ibf-solutions. New standard prEN 50742: Protection against corruption (last amended 5 October 2026).
  11. ibf-solutions. Postponement of Machinery Regulation cybersecurity and AI requirements (last amended 19 March 2026).