Concept illustration of glowing seats around a round table linked to a central shield, representing a one-day NIS2 risk assessment workshop

How to Run a NIS2 Risk Assessment Workshop: A One-Day Agenda, the 3 Things to Agree Beforehand and the 3 Sign-Offs That Follow

In short

  • A NIS2 risk assessment workshop is not named in the law: neither the Directive nor CIR 2024/2690 uses the word “workshop”. It is one way to produce what CIR point 2.1.2 asks for.
  • Fix three things before the day: the methodology, the risk tolerance and the risk criteria, points 2.1.2(a) to (c).
  • Three sign-offs follow: Article 20(1) approval of the measures, and CIR 2.1.1 acceptance of the results and of the residual risks.
  • Checked against: Directive (EU) 2022/2555, CIR 2024/2690 Annex 2.1, ENISA implementation guidance v1.0.

You have a date in the calendar, a meeting room and a list of people from IT, operations, procurement and finance. What you usually do not have yet is an agreement on what a “4 out of 5” likelihood means, or how much downtime counts as “severe”. If that gets settled on the day, the morning goes on the argument and the afternoon on rushed scoring.

This guide turns the risk management points of CIR 2024/2690 into a facilitated one-day workshop. It covers what has to be agreed beforehand, who sits in the room, an hour-by-hour agenda, and the outputs that go to the management body afterwards. Two related jobs are covered elsewhere: building the list of threats (our threat catalogue guide) and writing up the results (our risk assessment report template). This article links to them instead of repeating them.

Who is bound by which part of this?

Every essential and important entity must manage its risks under Article 21 of the NIS2 Directive, as transposed into national law. The detailed Annex points cited below bind only the entity types listed in Article 1 of Implementing Regulation (EU) 2024/2690; for everyone else they are a useful benchmark, not a legal duty.

Free Download

Get the NIS2 Article 21 Compliance Checklist

90+ assessment items mapped to CIR 2024/2690 — instant PDF, no payment.

✓ Check your inbox — the PDF is on its way.

Your entity What binds you How to use this agenda
DNS service provider, TLD name registry, cloud, data centre, CDN, managed service provider, managed security service provider, online market place, search engine, social network platform, trust service provider NIS2 Articles 20 and 21 via national law, plus CIR 2024/2690 Annex point 2.1 directly Follow it point by point; the CIR references are your obligations
Any other essential or important entity NIS2 Articles 20 and 21 via your national law Use the CIR points as a checklist of good structure; check your national act for approval wording
Not in scope No NIS2 duty The format still works for ISO 27001 or customer due-diligence assessments

The deciding question is simple: if your service type is in the first row, every “point 2.1.x” in this guide is binding on you; if not, it is the best available description of what a supervisor will expect a risk assessment to contain.

The law never says “workshop”: what the day has to produce

Counted over the English texts, “workshop” appears zero times in the Directive and zero times in the CIR. ENISA’s technical implementation guidance uses it three times, all about training and awareness. “Risk owner” appears in none of the three. What the CIR does require, in point 2.1.2, is a risk management process with ten elements, (a) to (j). A workshop is a good way to deliver most of them at once, because the people who know the risks are in one room. It cannot deliver all of them, and that split decides the shape of the day.

CIR point 2.1.2 What it requires When it happens
(a), (b), (c) Follow a methodology; set the risk tolerance level in line with the risk appetite; establish risk criteria Before the day, agreed and signed
(d) Identify risks on an all-hazards basis, in particular third parties and single points of failure On the day (seeded by pre-reads)
(e), (f) Analyse threat, likelihood, impact and risk level, using threat intelligence and vulnerabilities; evaluate against the criteria On the day
(g), (i) Identify and prioritise treatment options; name who implements and when On the day, in draft
(h), (j) Monitor implementation; document the treatment plan and the reasons for accepting residual risks Drafted at the end of the day, finalised after it

The table’s takeaway: three elements have to exist before anyone walks into the room, and two can only be finalised after it. A workshop that tries to finish all ten in one day will do none of them well.

Before the day: the three decisions the room must not re-argue

Sign the methodology, the tolerance and the scales off before the invitations go out. A rating scale that changes during the workshop makes every earlier score meaningless, and nobody will rescore the morning at 4 p.m.

1. The methodology, point 2.1.2(a)

The CIR names no method. ENISA’s advice is simply to “select a risk management methodology” and its evidence list asks for a methodology or tool covering at least elements (a) to (f). Whether you choose ISO 27005, NIST SP 800-30 or a national method, write down which one, which scoring formula, and which steps the workshop covers. If you are still choosing, our risk assessment guide compares the options for SMEs.

2. Tolerance and appetite, point 2.1.2(b)

Point (b) ties the tolerance level to the entity’s risk appetite, which is a business decision, not a security one. ENISA’s examples show the level of precision that helps on the day: “up to two hours of downtime per month” for critical systems, and “up to EUR 100,000 in recovery costs”. Get these numbers from the management body before the workshop; our guide to documenting risk appetite at board level shows how to record them.

3. The risk criteria and the two scales, point 2.1.2(c)

NIS2 defines risk in Article 6(9) as a combination of “the magnitude of such loss or disruption and the likelihood of occurrence”. So you need two scales, and each step on each scale needs a number, not just a word. NIST SP 800-30 describes organisations as typically annotating their scales “with organizationally-meaningful examples” and defining “break points between bins”. Its frequency bins for errors, accidents and acts of nature (Table G-3) are a ready starting point:

Likelihood level Frequency anchor (NIST SP 800-30, Table G-3)
5 Very high More than 100 times a year
4 High Between 10 and 100 times a year
3 Moderate Between 1 and 10 times a year
2 Low Less than once a year, but more than once every 10 years
1 Very low Less than once every 10 years

For deliberate attacks NIST uses a separate scale (Table G-2) based on whether an adversary is likely to initiate the event, and it expects a written rationale with each rating. Keep that column in your register: the rationale is what a reviewer reads a year later.

The impact scale is yours to write, because only you know what EUR 100,000 means to your balance sheet. A workable design has four columns per level: money, downtime of the critical service, data affected, and effect on the recipients of your services, which Article 21(1) names explicitly. Entities bound by the CIR can anchor the top band to the financial test for a significant incident in its Article 3(1)(a): direct financial loss above EUR 500,000 or 5% of total annual turnover, whichever is lower. Then the top band of your scale lines up with the point where you would also have to report the incident.

ENISA’s guidance also asks you to define risk acceptance criteria next to the risk criteria; write them in the same document. ENISA’s examples include “losses under EUR 50,000 accepted without further action” and accepting a known weakness for a set period while remediation is planned. Its guidance also says that risks from vulnerabilities in the highest severity class, such as “critical” under CVSS, should not be accepted “if possible”.

Why the scales need numbers, not just words

“Likely” means different things to different people, and the difference is large enough to change a risk’s ranking.

881 participants rated 29 Dutch probability and frequency phrases and showed large variability in what each phrase meant, among statisticians and non-statisticians alike.

Source: Willems, Albers and Smeets, Variability in the interpretation of Dutch probability phrases

The authors conclude that verbal probability expressions “may be a risk for miscommunication”. The European Food Safety Authority solved the same problem with a fixed approximate probability scale: “likely” is reserved for 66–90%, “unlikely” for 10–33%, and so on. EFSA also recommends stating the number first and the word second, because that order “leads to more consistent understanding”. Borrow the rule even if you keep your own bands: print the number before the label on every scale card in the room.

Pre-reads and silent pre-scoring, two weeks out

Send the pack ten working days ahead, and ask each risk owner to score their own risks alone before the day. A guide for utilities by the American Public Power Association advises sharing the risk register beforehand so participants have time to review it. Silent pre-scoring adds one more safeguard. A Lancaster University team that trialled a facilitated security risk workshop six times had participants write down possible risks individually, then discuss them. EFSA’s expert-elicitation protocols exist for a similar reason: to “counter psychological biases” when experts share and combine judgements.

The pre-read pack, with the CIR point each item feeds:

  • The signed methodology, tolerance, risk criteria and scales (2.1.2(a)–(c)), plus the acceptance criteria ENISA recommends.
  • Last cycle’s risk register and the list of significant changes and incidents since then, which are the review triggers of point 2.1.4.
  • The asset classification (point 12.1) and the business impact analysis (point 4.1.3), both of which point 2.1.3 tells you to use when prioritising treatment.
  • The threat catalogue, current threat intelligence and the open vulnerability list (2.1.2(e)).
  • The list of critical suppliers and service providers (2.1.2(d)).
  • Results of the last effectiveness review of your measures, which Article 21(2)(f) of the Directive requires you to have a procedure for.

Who sits in the room, and why

Invite the people who own the processes, not just the people who run the systems. The CIR has no “risk owner” but it does require you to name who implements each treatment measure and when (2.1.2(i)), and it lets “persons who are accountable and have the authority to manage risks” accept results under point 2.1.1. Those people should help produce the scores they will later sign.

Role Why they are needed Sessions Legal hook
Facilitator (not a risk owner) Keeps time and the method; stays neutral on scores All day 2.1.2(a) method followed
Business process owners Know the impact of losing their process All day 2.1.2(i), 2.1.1
IT and security lead Brings threat intelligence and vulnerabilities All day 2.1.2(e)
OT or facilities engineer, where you run plant Single points of failure and the physical environment Identification, analysis 2.1.2(d); Directive Art 21(2)
Procurement or vendor manager Supplier dependencies Identification, treatment 2.1.2(d); Directive Art 21(3)
Finance Prices the impact bands and the cost of treatment Analysis, treatment 2.1.3 cost versus benefit
One management-body member Hears the reasoning they will later approve Opening, calibration, final block Directive Art 20(1) and 20(2)
Note-taker Records scores, reasons and dissent All day 2.1.2(j) “comprehensible” reasons

The management-body member matters most and should speak least during scoring. Article 20(2) requires management-body members to follow training so they can “identify risks and assess cybersecurity risk-management practices”; sitting through calibration and the acceptance block gives them the concrete material to apply it to. A risk workshop is not designed as that training. ENISA does list “workshop and seminar attendance” among examples of evidence of management training, but check what your national authority accepts before counting it (see our guide to board training requirements). In practice, ask them to give their view last in each discussion, so the room does not simply follow the most senior person.

Keep scoring groups small. The APPA guide seats “4-6 participants” per table, assigns a note-taker, and tells the facilitator to “avoid expressing personal opinions”. In practice, that means eight to twelve people in total for most mid-sized entities, split into two tables.

The one-day agenda, hour by hour

The agenda below runs from 09:00 to 16:45 and follows the sequence of the main elements of CIR point 2.1.2. Each block ends with something written on the wall that the next block uses.

Time Block CIR point Output at the end
09:00–09:20 Opening: scope, the signed scales, what changed since the last review 2.1.4 List of review triggers
09:20–10:00 Calibration on two reference scenarios 2.1.2(c) Spread of individual scores and the agreed reading
10:00–11:15 Identification sweep 2.1.2(d) Risk list, including supplier and single-point-of-failure rows
11:15–11:30 Break – –
11:30–12:45 Analysis in two tables 2.1.2(e) Threat, likelihood, impact, level and rationale per risk
12:45–13:30 Lunch – –
13:30–14:15 Evaluation and ranking 2.1.2(f) Ranked list, marked above or within tolerance
14:15–15:30 Treatment options, owners and dates 2.1.2(g), (i); 2.1.3 Draft treatment plan rows
15:30–15:45 Break – –
15:45–16:30 Residual risks and acceptance reasons, with the management-body member 2.1.2(j); 2.1.1 Draft acceptance list with one reason per risk
16:30–16:45 Close: open items, owners, date of the approval meeting 2.1.2(h) Action log

Four blocks need a note on how to run them.

Calibration (09:20). Give everyone two short scenarios, one from your own incident history and one from the threat catalogue, and have them score both silently on the signed scales. Put the scores on the wall. A spread of two or more levels on the same scenario shows that people are reading the scale differently; settle that reading now, using the numbers on the scale cards, before any real risk is scored.

Identification (10:00). Point 2.1.2(d) names the blind spots of a typical IT-led session: third parties, single points of failure, and all four security properties, including authenticity. The Directive’s all-hazards approach in Article 21(2) also covers “the physical environment” of your systems. Walk the threat catalogue by category rather than brainstorming from a blank flipchart; our threat catalogue guide gives you the rows.

Analysis (11:30). Split the risk list between the two tables by business area, then bring them back together to compare. The APPA guide uses group reporting to “align scores and strategies, addressing any discrepancies between groups”. Every score gets a one-line reason, written while the room still remembers the argument.

Treatment (14:15). The CIR’s recital 11, which is explanatory rather than binding, names avoiding, reducing and, “in exceptional cases”, accepting the risk; ENISA adds transfer or sharing, for example through insurance, while noting that it does not remove the entity’s accountability. Point 2.1.3 adds cost against expected benefit, so keep finance at the table. Each draft row needs an owner and a date, or it fails point 2.1.2(i). Our guide to risk treatment plan options covers the choice in detail.

What leaves the room, and the three sign-offs that follow

The workshop produces drafts; approval happens afterwards, at a management-body meeting within a few weeks. The legal sources split the decisions in a way most templates blur:

Output Legal hook Who decides Evidence ENISA lists
Risk assessment results (ranked register with reasons) CIR 2.1.1 Management body, or accountable persons with adequate reporting to it Record of approval of risk assessment results
Risk treatment plan (measures, owners, dates) Directive Art 20(1); CIR 2.1.2(j) Management body under Art 20(1); ENISA also names accountable persons Documented risk treatment plan
Residual risks with acceptance reasons CIR 2.1.1, 2.1.2(j) Management body, or accountable persons with adequate reporting to it Record of approval of residual risks
Workshop record (attendance, calibration, dissent) None named; supports 2.1.2(a) Facilitator Key personnel knowing the main risks

Article 20(1) requires management bodies to “approve the cybersecurity risk-management measures” taken to comply with Article 21. Article 21(1), often cited alongside it, contains the duty to take the measures but no approval step. The treatment plan is where those measures are listed, which makes it the natural document for the Article 20(1) decision. Point 2.1.1 is the only place that allows delegation, and only for accepting the results and the residual risks, “provided that” the management body receives adequate reporting. ENISA’s guidance goes further and asks that the management body or accountable persons approve “the risk-assessment results and risk-treatment plan”.

National wording can differ. Germany’s § 38(1) BSIG obliges management to implement the risk-management measures (“umzusetzen”) and oversee their implementation; the verb “approve” from Article 20(1) does not appear in it. German minutes should therefore record management’s implementation decisions, not only a sign-off. Check the wording of your own national act before drafting the resolution.

Write the results up in the structure of our risk assessment report template, which puts both acceptances on one approval page, and file the residual-risk reasons as described in our guide to residual risk documentation.

Five ways the workshop fails an audit

Most weak workshops fail on process, not on missing risks. These are the five patterns that leave an auditor without the evidence the CIR describes:

  1. Scales changed on the day. Scores before and after the change are not comparable, and point 2.1.2(c) asks you to “establish and maintain” criteria, not reinvent them per meeting.
  2. Words without numbers. “Likely” and “severe” mean different things to finance and to IT; the Willems survey found wide variability among statisticians and non-statisticians alike.
  3. The most senior voice scores first. Without silent pre-scoring, the register records one person’s view with a group’s signature on it.
  4. An IT-only list. No supplier rows, no single points of failure, no authenticity, no physical events: all four are named in point 2.1.2(d) or Article 21(2).
  5. No acceptance record. Flipchart photos are not a decision. ENISA’s evidence list asks for records of approval of both the results and the residual risks.

The half-day version for a small entity

A 40-person company does not need two scoring tables. Keep the before-the-day work unchanged, because the scales and tolerance are what make the result defensible, and compress the day to four hours: 20 minutes of calibration, one combined identification and analysis block, then treatment and acceptance with the managing director present. Article 21(1) lets proportionality take account of the entity’s size and exposure to risks, so a shorter session fits a smaller entity, provided it still covers every element. The Lancaster team first set its own workshop a limit of one working day, then tightened it to less than half a working day; its sessions took 2 to 3 hours. Our hub on risk management implementation shows how the workshop fits the wider Article 21(2)(a) programme.

Frequently asked questions

Is a risk assessment workshop mandatory under NIS2?

No. Neither the Directive nor CIR 2024/2690 mentions a workshop. CIR point 2.1.2 requires a documented risk management process with elements (a) to (j); a workshop is one efficient way to produce the identification, analysis and evaluation parts with the right people.

Who has to approve the output of the workshop?

Under Article 20(1), the management body approves the risk-management measures; in practice the treatment plan is the most natural document to approve. For entities bound by CIR 2024/2690, point 2.1.1 requires the results and residual risks to be accepted by the management body or by accountable persons, provided the management body receives adequate reporting.

How often should we run it?

CIR point 2.1.4 requires the risk assessment results and treatment plan to be reviewed at planned intervals “and at least annually”, and after significant changes or significant incidents. A yearly workshop, plus a shorter session after any trigger, covers that pattern.

Should the whole board attend?

Usually not. One management-body member attending the opening, calibration and acceptance blocks is enough to carry the reasoning back to the approval meeting. The full body decides afterwards, on the written results.

Can the workshop run online?

Yes. The APPA guide covers virtual sessions with breakout rooms and shared scoring documents. Keep the silent pre-scoring step in an online session too.

Next step

Book the approval meeting before you book the workshop: a date with the management body forces the scales and tolerance to be signed in time, and gives the room a reason to finish its drafts. Then send the pre-read pack ten working days ahead.

This article provides general information only and does not constitute legal or regulatory advice. Requirements may vary by jurisdiction and organisation type. Consult a qualified legal professional or compliance specialist for advice specific to your situation.

Sources

  1. European Commission. Commission Implementing Regulation (EU) 2024/2690, Annex point 2.1 — risk management framework. EUR-Lex
  2. Directive (EU) 2022/2555 (NIS2). Article 20 — Governance. Official Journal text
  3. Directive (EU) 2022/2555 (NIS2). Article 21 — Cybersecurity risk-management measures. Official Journal text
  4. Directive (EU) 2022/2555 (NIS2). Article 6 — Definitions. Official Journal text
  5. ENISA. Technical Implementation Guidance on cybersecurity risk-management measures, version 1.0, June 2025. ENISA
  6. NIST. Special Publication 800-30 Rev. 1 — Guide for Conducting Risk Assessments. National Institute of Standards and Technology
  7. EFSA. Tutorial on Uncertainty — Approximate probability. European Food Safety Authority
  8. Willems, Albers and Smeets. Variability in the interpretation of Dutch probability phrases — a risk for miscommunication. arXiv
  9. American Public Power Association. Risk Assessment Workshop Guide for Public Power Utilities. APPA
  10. Weir, Dyson and Prince. A Lot Less Likely Than I Thought: Introducing Evidence-Based Security Risk Assessment for Healthcare Software. Lancaster University
  11. Federal Republic of Germany. BSI-Gesetz (BSIG) § 38 — duties of management. Gesetze im Internet