DORA Exit Strategy and Exit Plan: Article 28(8)’s Three Tests, the Article 30(3)(f) Transition Period and How to Test the Plan
In short
- A DORA exit strategy is required by Article 28(8) for ICT services supporting critical or important functions; RTS 2024/1773 Article 10 requires the third-party policy to set requirements for a documented exit plan for each such contract.
- You must be able to exit without disrupting the business, limiting regulatory compliance or harming client service.
- Contracts for critical or important functions need a mandatory adequate transition period (Article 30(3)(f)).
- Checked against: DORA, Delegated Regulation (EU) 2024/1773, Implementing Regulation (EU) 2024/2956.
An exit plan that says “we would move to another provider” falls short of DORA on its first page. Article 28(8) does not ask whether you could leave a critical ICT provider. It asks whether you could leave without disrupting your business, without limiting your compliance and without hurting your clients, and it wants documented, tested plans that prove it. This guide separates the strategy from the plans, lists the exit triggers in DORA and its technical standards beyond Article 28(7), sets the transition period against the EU Data Act’s 30-day switching window, and shows how to test a plan when the law sets no testing frequency.
Who needs an exit strategy, and who the RTS plan rules reach
In plain terms: every financial entity under DORA needs exit strategies for ICT services that support critical or important functions. The more detailed plan rules in RTS 2024/1773 reach a narrower group, because they sit inside a policy that microenterprises and Article 16(1) entities do not have to write.
A critical or important function is one whose disruption “would materially impair” the entity’s financial performance, the soundness or continuity of its services, or its continuing compliance with its authorisation (DORA Article 3(22)). Article 28(8) contains no carve-out for small firms; it is applied in proportion to size and risk profile through Article 4(2). The RTS is different. Delegated Regulation (EU) 2024/1773 specifies the content of the Article 28(2) policy, and Article 28(2) excludes microenterprises and the entities in Article 16(1). On our reading, the RTS Article 10 wording therefore binds only entities that must write that policy, while everyone else still owes the Article 28(8) duties directly.
Get the NIS2 Article 21 Compliance Checklist
90+ assessment items mapped to CIR 2024/2690 — instant PDF, no payment.
| Duty | Full-framework entities | Microenterprises | Article 16(1) entities |
|---|---|---|---|
| Termination rights in every ICT contract (Art 28(7)) | Yes | Yes | Yes |
| Exit strategies, tested exit plans, alternatives, transition plans for critical or important functions (Art 28(8)) | Yes | Yes, proportionate (Art 4(2)) | Yes, proportionate (Art 4(2)) |
| Policy requiring one documented exit plan per arrangement that takes three scenarios into account (RTS 2024/1773 Art 10) | Yes | No policy duty (our reading) | No policy duty (our reading) |
| Transition period clause in critical contracts (Art 30(3)(f)) | Yes | Yes | Yes |
| “Existence of an exit plan” field in the register (ITS 2024/2956, B_07.01.0080) | Yes | Yes | Yes |
For suppliers that fall outside DORA’s ICT third-party rules, see our guide to the NIS2 supply chain gap for financial entities. If you are still working out whether DORA applies at all, start with what DORA is and who it covers.
Strategy versus plan: the five things Article 28(8) asks for
In plain terms: Article 28(8) has five subparagraphs, and each one asks for a different document or capability. Most exit documents cover the first and skip the rest.
| Art 28(8) | What the text requires | What it means on paper |
|---|---|---|
| 1st subpara | “put in place exit strategies” that take into account provider failure, deteriorating quality, business disruption from failed provision, material deployment risk, or termination under Article 28(7) | An entity-level strategy that names the risks and the exit routes |
| 2nd subpara | Be “able to exit contractual arrangements without” disruption to business activities, limiting compliance with regulatory requirements, or detriment to the continuity and quality of client services | Three pass criteria every plan is tested against (next sections) |
| 3rd subpara | “Exit plans shall be comprehensive, documented and, in accordance with the criteria set out in Article 4(2), shall be sufficiently tested and reviewed periodically” | Written plans, a test record, a review date |
| 4th subpara | “identify alternative solutions and develop transition plans” to remove the services and data and “securely and integrally transfer them to alternative providers or reincorporate them in-house” | A named alternative or an insourcing route, plus a data transfer method |
| 5th subpara | “appropriate contingency measures in place to maintain business continuity” in the circumstances of the first subparagraph | A link to the business continuity plan for the period before the exit completes |
RTS 2024/1773 then makes the plan granular. Its Article 10 requires “a documented exit plan for each contractual arrangement” and its “periodic review and testing”, and the RTS defines a contractual arrangement as one covering ICT services that support critical or important functions. So a bank with three separate critical contractual arrangements with the same cloud provider writes three plans, not one. The same article sets the quality bar: the plan “shall be realistic, feasible, based on plausible scenarios and reasonable assumptions” with “a planned implementation schedule compatible with the exit and termination terms established in the contractual arrangements”.
Exit triggers: Article 28(7) and four more provisions
In plain terms: Article 28(7) is the best-known list of reasons to leave, but your strategy has to cover triggers from four other provisions too, and one of them is a decision your supervisor takes, not you.
Article 28(7) itself applies to all contractual arrangements on the use of ICT services, not only critical ones. Every ICT contract must be terminable for a significant breach of laws, regulations or contract terms; for circumstances found through monitoring “that are deemed capable of altering the performance of the functions provided”; for evidenced weaknesses in the provider’s ICT risk management, especially around data availability, authenticity, integrity and confidentiality; and where the competent authority “can no longer effectively supervise” the entity because of the arrangement.
| Trigger | Source | Planned or sudden exit? |
|---|---|---|
| Four termination circumstances (a) to (d) | DORA Art 28(7) | Usually planned: you choose to terminate |
| Provider failure, quality deterioration, business disruption, deployment risk | DORA Art 28(8), 1st subpara | Often sudden |
| Unforeseen and persistent interruptions; inappropriate or failed delivery; unexpected termination | RTS 2024/1773 Art 10(a) to (c) | Sudden; the plan must still run |
| Provider implements subcontracting changes you objected to, implements them before the notice period ends without approval, or subcontracts a critical service the contract does not explicitly permit | Delegated Regulation (EU) 2025/532 Art 6 | Planned, but often at short notice |
| Authority requires termination of contracts with a critical ICT third-party provider | DORA Art 42(6) | Imposed; Art 42(8) says authorities shall grant “the necessary period of time” to deploy exit strategies and transition plans |
The last row is the one most strategies miss. Under Article 42(6), a competent authority may, “as a measure of last resort”, require suspension and, where necessary, termination of contracts with a provider designated as critical. The regulation promises time to adjust, but the exit strategy is the document that decides how much time you would need. The RTS on subcontracting adds a contractual hook: Article 4(1)(l) requires the contract to give you the right to terminate when either its Article 6 conditions or the Article 28(7) conditions are met.
The ECB Guide on outsourcing cloud services (July 2025, non-binding) suggests further grounds for its supervised entities to consider, including a merger or sale of the provider, relocation of its head office to another jurisdiction or of its data centre to another country, and continuous failure to meet service levels. It also says that where a contract covers services that can be managed independently, it should be possible, “where feasible and beneficial”, to terminate only some of them.
The three “without” tests, turned into pass criteria
In plain terms: the second subparagraph of Article 28(8) is the real test of an exit plan. Write each of its three limbs as a measurable criterion, and the plan becomes something you can test.
| Exit without… | What fails the test | Evidence to keep |
|---|---|---|
| (a) disruption to business activities | The migration window is longer than the transition period, or the target platform has never been sized | Migration time estimate compared with the contractual transition period; capacity check of the alternative |
| (b) limiting compliance with regulatory requirements | Records, logs or audit trails stay with the old provider; the new location breaks data-location rules; the register is not updated | Data inventory with retention periods; check of the new provider against Article 30 terms; register change log |
| (c) detriment to continuity and quality of client services | Clients lose access, payments queue, or service levels drop during cut-over | Cut-over plan with client-facing service levels; communication plan; fallback step |
The three limbs need different owners. A CISO can show that data moves “securely and integrally”. Only a compliance officer can show that regulatory records survive the move, and only the business owner can say what client-service drop is tolerable. That split is why an exit plan written by IT alone tends to pass limb (a) and miss (b) and (c).
Keep exit and continuity apart, too. Article 28(8)’s last subparagraph requires contingency measures for the same risks, and the ECB guide draws the line in one sentence: “While BCM measures should ensure the continuity of services in the short term, exit plans should ensure continuity in the long term.” The business continuity plan keeps the function running on day one; the exit plan moves it somewhere it can stay.
The transition period: Article 30(3)(f) and the Data Act’s 30 days
In plain terms: your contract must oblige the provider to keep running the service while you leave. For cloud services, the EU Data Act now sets its own switching clock, and the two need to line up.
Article 30(3)(f) requires contracts for critical or important functions to include “exit strategies, in particular the establishment of a mandatory adequate transition period”, during which the provider “will continue providing the respective functions, or ICT services”, and which allows you “to migrate to another ICT third-party service provider or change to in-house solutions consistent with the complexity of the service provided”. DORA sets no number of days. “Adequate” is measured against your own migration estimate, which is why the plan has to exist before the contract is negotiated. Two baseline clauses in Article 30(2) carry the rest: point (d) on access, recovery and return of data “in an easily accessible format” on insolvency, resolution, discontinuation or termination, and point (h) on termination rights and minimum notice periods.
The Data Act (Regulation (EU) 2023/2854) has applied since 12 September 2025 and covers what it calls data processing services: on-demand, scalable and elastic computing resources (Article 2(8)). Its Article 25 requires switching contracts to include:
- a maximum notice period for starting the switch that “shall not exceed two months” (Article 25(2)(d));
- a “mandatory maximum transitional period of 30 calendar days”, starting after that notice period, during which the contract remains applicable and the provider must “act with due care to maintain business continuity” (Article 25(2)(a));
- a data retrieval period “of at least 30 calendar days” after the transitional period (Article 25(2)(g));
- “an obligation of the provider of data processing services to support the customer’s exit strategy relevant to the contracted services, including by providing all relevant information” (Article 25(2)(b)).
30 calendar days is the Data Act’s mandatory maximum transitional period for switching a cloud-type service, extendable once by the customer.
Source: Regulation (EU) 2023/2854, Article 25(2)(a) and 25(5)
On our reading, the 30 days are a ceiling on how long the provider may take to complete a switch, not a cap on your DORA transition period. If 30 days is technically unfeasible, the provider must say so within 14 working days and propose an alternative period of up to seven months (Article 25(4)). Article 25(5) also gives the customer the right “to extend the transitional period once for a period that the customer considers more appropriate for its own purposes”. A financial entity whose migration estimate is longer than 30 days should write its adequate period into the contract and record how it will use that extension right. From 12 January 2027, providers “shall not impose any switching charges” for the switching process (Article 29(1)); until then, charges may not exceed the provider’s direct switching costs. Any switching charges until then belong in the plan’s cost estimate.
Two limits keep this honest. The Data Act covers cloud-type services only, so a core banking licence or a managed security service may sit outside it. And for services custom-built for one customer and not offered at broad commercial scale, Article 31(1) lifts the switching-charge rule and some technical obligations, though not Article 25.
What goes into each exit plan
In plain terms: each plan answers five questions for one arrangement: where the service goes, how the data gets there, how long it takes, who does the work, and what it costs.
| Plan section | Content | Anchor |
|---|---|---|
| Scope and scenarios | The arrangement, the functions it supports, and how the plan runs under each of the three RTS scenarios | RTS Art 10(a) to (c) |
| Exit route | Named alternative provider or insourcing route, with the reason it is realistic | Art 28(8), 4th subpara; RTS Art 10 |
| Data and assets | Inventory of data, configurations and logs to move; format; transfer method; integrity check; deletion at the old provider | Art 28(8), 4th subpara; Art 30(2)(d) |
| Schedule | Critical milestones, time estimate, and a check that it fits the notice and transition periods | RTS Art 10; Art 30(3)(f); ECB guide 2.4.3 |
| People | Tasks and skillsets; internal staff or external help | ECB guide 2.4.3 |
| Cost | Rough estimate, including switching and egress charges and double-running | ECB guide 2.4.3 |
| Contingency link | Which business continuity measures cover the period before the exit completes | Art 28(8), 5th subpara |
| Test and review | Test method, last test date, findings, next review | Art 28(8), 3rd subpara |
The ECB treats “the critical milestones, a description of the tasks and skillsets that are required to perform the exit, and a rough estimate of the time required, and the costs involved” as the good-practice minimum, and recommends a regularly updated list of qualified alternative providers where the route is a move rather than insourcing. It also says exit strategies for critical cloud services, with roles and estimated costs, should be drawn up “before those systems go live”. That timing matters: the realism test in RTS Article 10 is far easier to pass when the exit route shaped the contract than when it is written around a contract already signed.
Testing an exit plan when the law sets no frequency
In plain terms: DORA says exit plans must be “sufficiently tested and reviewed periodically”, in proportion to the entity, and sets no interval. You pick the method and frequency, and you need to be able to defend both.
There is no yearly exit-test rule, unlike Article 11(6)(a), which requires business continuity plans to be tested “at least yearly”. The ICT risk management RTS (EU) 2024/1774 gives a useful overlap: Article 25(2) requires continuity testing to include ICT services provided by third parties where applicable, and to “duly consider scenarios linked to insolvency or failures of the ICT third-party service providers”. A provider-failure scenario in the continuity test can exercise the first days of an exit plan at the same time.
The ECB guide describes a ladder of depth. It treats “an in-depth desktop review” as the minimum, by staff with sufficient expertise in cloud technologies, and adds a review of the volume of data and the complexity of the applications to move, a walkthrough of the tasks with the staff who would perform them, periodic testing of “the most critical steps in the migration process”, and independent verification by “someone who is not responsible for drafting the plan in question”. A proportionate programme, in our suggestion rather than any rule, sets depth by how hard the provider is to replace:
| Substitutability recorded in the register | Suggested test | Effort |
|---|---|---|
| Easily substitutable | Desktop review at each policy or contract review | Low |
| Medium complexity | Desktop review plus a data-export test: export, then check completeness and readability outside the provider | Medium |
| Highly complex or not substitutable | Walkthrough with the people named in the plan, plus a technical test of the critical migration steps; independent review of the result | High |
The export test earns its place because a desktop review cannot show what an export leaves behind. A provider may export the data without the configuration, the audit logs or a format the alternative can read, and the plan’s time estimate depends on exactly those details.
| Role | Owns |
|---|---|
| Management body | Approves and periodically reviews the policy on ICT third-party arrangements (Art 5(2)(h)) and hears exit-test findings |
| CISO / ICT function | Data transfer method, technical tests, security during migration |
| Business owner | Client-service criteria (limb (c)) and the cut-over window |
| Compliance / legal | Regulatory records (limb (b)), Article 30 terms, notice periods, register entries |
| Independent reviewer (second line or internal audit) | Feasibility check of each plan, as the ECB guide recommends |
Recording the exit in the register of information
In plain terms: the register asks a set of exit-related questions about every ICT service that supports a critical or important function, and the answers have to match your plans.
Template B_07.01, “Assessment of the ICT services”, in Implementing Regulation (EU) 2024/2956 holds them:
| Column | Question | Options |
|---|---|---|
| B_07.01.0050 | Substitutability of the provider | Not substitutable; highly complex; medium complexity; easily substitutable |
| B_07.01.0060 | Reason if not or hardly substitutable | Lack of real alternatives; migration difficulties; both |
| B_07.01.0080 | Existence of an exit plan | Yes; No |
| B_07.01.0090 | Possibility of reintegration (not for intra-group providers) | Easy; difficult; highly complex |
| B_07.01.0100 | Impact of discontinuing the service | Low; medium; high; assessment not performed |
| B_07.01.0110 | Alternative providers identified? | Yes; No; assessment not performed |
Two details catch filers out. For column 0110 the ITS says that for each provider supporting a critical or important function “the assessment to identify an alternative service provider shall be performed”, so “assessment not performed” is an admission rather than a neutral answer. And the corrigendum of 19 September 2025 renumbered that option from “7” to “3”, so templates built before then may carry the old code. Column 0120 can name the alternative when 0110 is “Yes”. Our register of information guide walks the rest of the templates.
Common gaps, and the effort to close them
| Current state | Required state | Effort |
|---|---|---|
| One exit document per provider | One documented plan per contractual arrangement (RTS Art 10) | Medium |
| Termination clauses only in critical contracts | Art 28(7) termination rights in every ICT contract | Medium |
| Contract silent on transition, or a period shorter than the migration estimate | Mandatory adequate transition period (Art 30(3)(f)), checked against the plan | High |
| “Alternative: market” with no names | Alternative solutions identified (Art 28(8)); register field 0110 answered | Low |
| Plan never tested | Test record, findings and review date (Art 28(8), 3rd subpara) | Medium |
| Register says “Yes” to an exit plan that covers a different service | Register answers that match the plan for that specific service | Low |
The DORA ICT third-party risk policy guide covers the policy text that Article 10 sits in, and the guide to the simplified ICT risk framework covers what Article 16(1) entities owe instead.
FAQ
Do we need an exit plan for every ICT provider?
No. Article 28(8) requires exit strategies for ICT services supporting critical or important functions, and RTS 2024/1773 Article 10 requires one plan per such arrangement. Every ICT contract still needs the Article 28(7) termination rights.
How often must a DORA exit plan be tested?
DORA sets no interval. Plans must be “sufficiently tested and reviewed periodically” in proportion to the entity under Article 4(2). Set the frequency by how hard the provider is to replace, and record why.
Does a microenterprise need an exit strategy?
Yes, on our reading. Article 28(8) has no microenterprise carve-out, but it applies in proportion to size and risk profile. The microenterprise is outside the Article 28(2) policy that RTS 2024/1773 details.
Is an exit plan the same as a business continuity plan?
No. Continuity measures keep a function running during a disruption; the exit plan moves the service and its data to an alternative or in-house. Article 28(8) asks for both.
Can we use the cloud provider’s offboarding guide as our exit plan?
Only as an input. The Data Act obliges cloud providers to support your exit strategy, but under DORA Article 28(1)(a) the financial entity remains “fully responsible” for its obligations, so the plan, its tests and its assumptions are yours.
What to do next
Pull the B_07.01 rows for every ICT service supporting a critical or important function and sort them by substitutability. For the hardest-to-replace provider, write the migration estimate first and compare it with the notice and transition periods in the contract; if the estimate is longer, that is the clause to renegotiate before anything else. Then schedule a data-export test for that provider and record the result. The DORA compliance hub shows how the exit plans connect to the policy, the register and the Article 30 contract terms.
This article provides general information only and does not constitute legal or regulatory advice. Requirements may vary by jurisdiction and organisation type. Consult a qualified legal professional or compliance specialist for advice specific to your situation.
Sources
- Regulation (EU) 2022/2554 on digital operational resilience for the financial sector (DORA), Articles 3(22), 4(2), 5(2)(h), 11, 16(1), 28, 30 and 42. EUR-Lex, OJ L 333, 27.12.2022.
- Commission Delegated Regulation (EU) 2024/1773 on the policy for ICT services supporting critical or important functions, Articles 1 and 10. No corrigendum listed on EUR-Lex (checked 9 November 2026).
- Commission Delegated Regulation (EU) 2024/1774 on ICT risk management tools, methods, processes and policies, Articles 25 and 26; its EN corrigendum of 15 May 2025 affects Article 22 only.
- Commission Implementing Regulation (EU) 2024/2956 on standard templates for the register of information, template B_07.01.
- Corrigendum to Implementing Regulation (EU) 2024/2956, OJ L 2025/90725, 19.9.2025.
- Commission Delegated Regulation (EU) 2025/532 on subcontracting ICT services supporting critical or important functions, Articles 4 and 6.
- Regulation (EU) 2023/2854 (Data Act), Articles 2(8), 25, 29, 31 and 50.
- European Central Bank, Guide on outsourcing cloud services to cloud service providers, July 2025, section 2.4 (non-binding).